On January 27, 2020, FERC petitioned the United States Court of Appeals for the Sixth Circuit (“Sixth Circuit”) for rehearing en banc of that court’s decision finding bankruptcy court-FERC concurrent jurisdiction over certain power purchase agreements. Notwithstanding such concurrent jurisdiction, the Sixth Circuit’s decision finds that the bankruptcy court’s concurrent jurisdiction is paramount, and that therefore, FERC-jurisdictional power purchase agreements are susceptible to rejection in bankruptcy.
The recent chapter 11 filings by PG&E Corp. and its Pacific Gas & Electric Co. utility subsidiary (collectively, "PG&E") and FirstEnergy Solutions Corp. have reignited the debate over the power of a U.S. bankruptcy court to authorize the rejection of contracts regulated by the Federal Energy Regulatory Commission ("FERC"). Only a handful of courts have addressed this thorny issue to date, and with conflicting results in a controversy that may ultimately need to be resolved by the U.S. Supreme Court or legislative action.
In orders issued on January 25 and 28, 2019, FERC concluded that the Commission and the bankruptcy courts have concurrent jurisdiction to review and address the disposition of FERC-jurisdictional contracts sought to be rejected through bankruptcy and, therefore, a party to a FERC-jurisdictional wholesale power agreement must first obtain approval from both FERC and the bankruptcy court to modify the filed rate and reject the filed wholesale power contract, respectively. FERC made its determination in response to two separate petitions (“Petitions”) filed by NextEra Energy, Inc.
After months of speculation, it is now official : PG&E (both the parent, PG&E Corporation, and its subsidiary, Pacific Gas & Electric Company), having faced extraordinary challenges relating to catastrophic wildfires in 2017 and 2018, has announced that a voluntary bankruptcy filing “is appropriate, necessary and in the best interests of all stakeholders, including wildfire claimants, PG&E’s other creditors and shareholders, and is ultimately the only viable option to restore PG&E’s financial stability to fund ongoing operations and provide safe service to customers.” As
On January 25, 2019, the US Federal Energy Regulatory Commission (“FERC” or “Commission”) issued an order clarifying its position with regard to bankruptcy filings that seek to reject Commission-jurisdictional wholesale power purchase agreements. In response to a petition for a declaratory order and complaint filed by NextEra Energy, Inc. and NextEra Energy Partners, L.P.
In a closely watched battle between FirstEnergy Solutions (“FirstEnergy”) and the Ohio Valley Energy Corporation (“OVEC”) that could have significant implications for the U.S. power sector, the U.S. Bankruptcy Court for the Northern District of Ohio asserted its primacy over the Federal Energy Regulatory Commission (“FERC”) in deciding whether to allow FirstEnergy to repudiate certain FERC-regulated power purchase agreements (“PPAs”).
On January 27, 2020, FERC petitioned the United States Court of Appeals for the Sixth Circuit (“Sixth Circuit”) for rehearing en banc of that court’s decision finding bankruptcy court-FERC concurrent jurisdiction over certain power purchase agreements. Notwithstanding such concurrent jurisdiction, the Sixth Circuit’s decision finds that the bankruptcy court’s concurrent jurisdiction is paramount, and that therefore, FERC-jurisdictional power purchase agreements are susceptible to rejection in bankruptcy.
In orders issued on January 25 and 28, 2019, FERC concluded that the Commission and the bankruptcy courts have concurrent jurisdiction to review and address the disposition of FERC-jurisdictional contracts sought to be rejected through bankruptcy and, therefore, a party to a FERC-jurisdictional wholesale power agreement must first obtain approval from both FERC and the bankruptcy court to modify the filed rate and reject the filed wholesale power contract, respectively. FERC made its determination in response to two separate petitions (“Petitions”) filed by NextEra Energy, Inc.
On January 25, 2019, the US Federal Energy Regulatory Commission (“FERC” or “Commission”) issued an order clarifying its position with regard to bankruptcy filings that seek to reject Commission-jurisdictional wholesale power purchase agreements. In response to a petition for a declaratory order and complaint filed by NextEra Energy, Inc. and NextEra Energy Partners, L.P.
After months of speculation, it is now official : PG&E (both the parent, PG&E Corporation, and its subsidiary, Pacific Gas & Electric Company), having faced extraordinary challenges relating to catastrophic wildfires in 2017 and 2018, has announced that a voluntary bankruptcy filing “is appropriate, necessary and in the best interests of all stakeholders, including wildfire claimants, PG&E’s other creditors and shareholders, and is ultimately the only viable option to restore PG&E’s financial stability to fund ongoing operations and provide safe service to customers.” As